5 Management Responsibility
|
5 Management
Responsibility
5.1 Management Commitment
Top
management shall provide evidence of its commitment to the development and implementation of the
quality management system and continually improving its effectiveness by:
a)
communicating to the organization the importance of meeting customer as well as statutory and
regulatory requirements,
b)
establishing the quality policy,
c)
ensuring that quality objectives are established,
d)
conducting management reviews, and
e)
ensuring the availability of resources.
|
ISO
9001 Training - Key Explanation Points and Tips:
Management commitment - relates to the responsibility of
top management to provide leadership
and direction for quality management within the organization. They must establish strategic quality management
policies, directives and objectives consistent with the purpose and capabilities of the organization. They must
establish the organizational structure and internal environment that motivates personnel to achieve the
organization's quality management goals and objectives. They must provide adequate resources to develop, implement,
maintain and improve the QMS. They must periodically review QMS performance to determine it suitability, adequacy
and effectiveness.
The above
activities are all requirements of clause 5. Each sub-clause of clause 5 starts with the phrase
“top management”. Top
management is now clearly accountable and auditable for their role and responsibilities for the activities listed
in the paragraph above.
The phrase “provide evidence” is very important here.
Auditors are expected to review documents and records showing top managements role in planning, implementing
and maintaining the QMS. Auditors will spend significant time auditing management for the requirements of clause
5.
You must begin with identifying
the processes within your
organization that perform these activities. These processes would typically include - business planning;
quality planning; management review; internal communication; organization structure; etc. Business planning
would address 5.1b and 5.1c, and so on for the other sub-clauses. Top management would be the process owner
of all these processes.
Clause 5.1a - may be viewed in
combination with clause 5.2 customer focus, and clause 5.5.3 internal
communication. Top management must communicate regularly to the organization on the importance of meeting
customer and regulatory requirements. The communication process should define what needs to be
communicated; to whom; the methods used; the frequency; and the means for determining communication
effectiveness. (See clause 4.1a- 4.1f for guidance in developing such a process.). Top management may
communicate in any number of ways including meetings; documented policies; memos; directives; email;
computer, etc.
Note: effectiveness may be measured by
asking - how much of the planned activities did we get done? Or to what extent did we achieve planned
results?
Clause 5.1 does
not require a ‘documented’ procedure. However, you must identify and document (e.g. process map; process flow
diagram; etc.) the processes for business planning; quality planning; management review; internal communication;
organization structure; etc. as part of your QMS (see clause 4.1). You must also identify what specific
documents are needed for
effective planning, operation and control of these processes (see clause 4.2.1d). These documents may include - a
documented procedure; business plan; statement of policies and objectives;
etc.
Look at the risks related to your
business, products, processes and resources in determining the nature and extent of documented controls you
need to have (also see clause 4.2.1 notes) for this clause.
Where some of clause 5 activities are performed off-site (e.g. at head-office), your QMS
must identify the off-site processes within your QMS and ensure that such processes comply with ISO 9001
requirements. Evidence of compliance may include - a copy of their ISO 9001 certification; ISO 9001 internal
audit results (of these processes) for the off-site facility; auditing these processes at the off-site
facility. The expectation is to flow down to the off-site facility, the relevant ISO 9001requirements that
you would have to implement, had you carried out the process at your own facility.
The specific
requirements for clause 5.1b through 5.1d will be discussed in the upcoming
sub-clauses.
|